Location:
Aberdeen
Proving Ground,
Md.
Owner:
U.S.
Army Corps of Engineers, Philadelphia District
Contractor: James G. Davis
Construction Corp.,
Rockville
,
Md.
Electrical: Enterprise Electric
Company
Architect:
EwingCole,
Philadelphia
Start Date: September 2009
Completion Date: February 2011
A
new $102-million Command Control/Communications Network (C2/CNT)
East Facility at the Command, Control, Communications,
Computers, Intelligence, Surveillance, Reconnaissance (C4ISR)
campus at Aberdeen Proving Ground, Md., will provide office and
research space to accommodate 1,900 personnel.
James
G. Davis Construction Corp. of Rockville, Md., began
construction in September on the project, which includes a
485,000-sq-ft, three- and four-story base building and an
adjacent 52,000-sq-ft, two-story building with additional
laboratories and computer facilities. The smaller building will
connect to the primary building with an enclosed two-level
bridge.